Skip to content
Home » Furnace Control & Instrumentation Design

Furnace Control & Instrumentation Design

1) Project overview:

Industry: Oil & Gas
System: Process Furnace (catalytic reforming)
Scope: Instrumentation + Control System Design + Site Support

This project covered the full control and instrumentation scope for a fired heater serving a catalytic reforming (platforming) unit. The solution provides safe start-up and shutdown sequences, stable temperature control, burner and fuel-gas management, and an integrated emergency shutdown system, designed in accordance with applicable industrial safety standards.


2) Process & control objective

The furnace had to:

  • Maintain stable outlet temperature
  • Control fuel and air ratio
  • Monitor flame and combustion
  • Protect the unit against unsafe conditions
  • Interface with the plant control system (DCS), Emergency shut-down system (ESD) and burning management system (BMS).

3) System architecture (P&ID)

  • Field instruments (temperature, pressure, flow, flame detection)
  • Valves (shut-off valves, control valves with positioner)
  • DCS-based control system
  • Emergency shut-down system (ESD)
  • Burner management system (BMS)
  • Operator SCADA
  • Safety interlocks and alarms
P&ID of the system

4) Instrumentation scope

Key instruments designed and specified:

  • Temperature, pressure, flow, level transmitters
  • Gas analyzers
  • Flame detectors
  • Valves (Control, shut-off valves and pressure safety valves)
Loop diagram

5) Control philosophy

The furnace was controlled using a layered strategy:

  • Temperature control loop regulating firing rate
  • Fuel-to-air ratio control for combustion stability
  • Start-up and shutdown sequencing
  • Trip and interlock logic to prevent unsafe operation
Block diagram

6) Engineering documents produce

  • P&ID
  • Loop diagrams
  • Instrument datasheets
  • Instrument index
  • I/O list
  • Control philosophy
  • Interconnection diagrams
  • Junction box wiring
  • Hook-up drawing
  • Cable data sheet and cable list
  • Cause&Effect chart
  • Site commissioning and test sheets
Hook-up drawing
I/O list

7) Factory acceptance test (FAT)

A Factory Acceptance Test (FAT) was performed to verify the complete functionality of the furnace control package prior to site installation, covering the control system, field devices, and local interfaces.

  • Control system functionality (logic, sequences, alarms, interlocks)
  • Control valve functional checks (actuation, positioning response, fail action)
  • Shut-off valve verification (open/close command, feedback, fail-safe behavior)
  • Local panel checks (wiring, indications, selector switches, local commands)
  • I/O verification and signal simulation where applicable
I/O signal cabinet
Testing cabinet
Control valve dimension check
Self-regulated valve check

8) On-site engineering

On-site activities included:

  • Instrument installation verification
  • Loop checking
  • DCS,ESD,BMS I/O testing
  • Support during commissioning
  • Troubleshooting signal and control issues
New instruments installed

9) Result

The furnace control system was successfully implemented and prepared for safe operation, with all safety, control, and monitoring functions validated during commissioning.

Finish – working furnace